Daubeney Primary School
Fact Sheet
Title
Daubeney Primary School Experimental Playground Project
Artist
Hattie Coppard
Landscape Architect
Lynn Kinnear, Kinnear Landscape Architects
Commissioner
Hackney Wick Public Art Programme
Commenced
March 2000
Completed
Construction completed June 2003
Location
Daubeney Primary School, Daubeney Road, London E5 5SN
Scope
77.4m x 34.4m
Materials
Various including: stainless steel, epoxy resin paint, wood, planting, light, textile screens, resin.
Total Project Commissioning Budget
£100,000 (approximately)
Funding sources
National Lottery New Opportunities Fund
Hackney Wick Single Regeneration Budget Partnershipadministered by Renaisi.
Summary Artists’ Brief
To develop a creative programme of consultationand participation with the school, leadingto ideas forimprovements to their playground.Subsequentlyto collaborate on developingdetailed designs inspired by the outcomesof theExperimental Playground Project.
Project Manager
Lucy McMenemy, Curator, Hackney Wick PublicArt Programme
Structural Engineers
Jim Dunn, Adams Kara Taylor
Steel Manufacturers
James Garner, Steve Lewis Steelworks
Specialist Paint Manufacture/Installation
Ryebrook Resins
Contractor
Baylis
Contact for further information
Lucy McMenemy, Curator, Hackney Wick Public Art Programme, London Borough of Hackney.
Tel/Fax: 020 8356 7358
E mail: [email protected]
Communications Department, The Learning Trust. Tel: 020 8820 7634